Things are still progressing, the floorboards has slowed things up a bit and caused the most delays however they should be installed next Monday and should take a couple of days to finish off. This week the driveway is meant to be started if not finished depending on the weather. Apparently the site was scheduled to be cutout for the driveway today.
The rendered section at the front of the house is also planned to be painted by the end of this week all things going well. There are a few other items that need attention including:
- Deadlock fitted to rear garage door
- Painting touch-ups
- Check plumbing to sinks
- Check mortar on one side of the house which looks discoloured
- Check expansions joints, there is one missing
- Install double glazed tri-stacker doors
I'll see if I can get some updated pictures soon, at this stage it probably won't be until the weekend.